Switchyard Design Checklist

0
189
Switchyard Design Checklist
Switchyard Design Checklist

This post provides a structured checklist for reviewing the design and validating the design of electrical switchyards.

This checklist provides general guidance for planning and reviewing electrical switchyard designs.

• Relevant IEC standards (IEC 61936-1 & IEC 60529). 

• Relevant IEEE standards (IEEE 80 & IEEE 81).

• National electrical regulations & safety rules.

• Utility or grid operator requirements.

• Applicable engineering design guides.

The overall switchyard design must be developed by considering the following aspects:

  • The required switchyard voltage level must be identified based on the system requirements.
  • The power input and output capacity must be determined according to the project load demand.
  • The incoming and outgoing power transmission lines must be confirmed and incorporated into the electrical design.
  • The switchyard location and orientation must be selected with respect to the overall power plant layout and transmission line paths.
  • An appropriate switching scheme as per NEMA SG-4 & NEMA SG-6 must be selected considering system reliability, maintenance flexibility and cost.
  • The system fault level information must be obtained from the utility (or) system studies.
  • The design short circuit level for the switchyard equipment must be established accordingly.
  • The Basic Insulation Level (BIL) must be determined based on the system voltage and insulation coordination requirements.
  • The required electrical clearances must be established based on the voltage level and insulation requirements.
  • The busbar type must be selected whether rigid busbar (or) flexible conductor busbar.
  • Major switchyard equipment such as circuit breakers, isolators, current transformers (CTs), voltage transformers (PTs) and lightning arresters must be selected.
  • The switchyard type must be determined such as Gas Insulated Switchgear (GIS), Air Insulated Switchyard (AIS), outdoor switchyard (or) indoor switchyard.
  • The environmental and pollution levels at the project site must be evaluated.
  • The insulator creepage distance requirements must be determined based on the pollution severity.
  • The necessary safety and regulatory requirements must be identified and incorporated into the design.

The detailed design of the switchyard must consider the following parameters:

  • The required phase-to-ground and phase-to-phase clearances must be established according to the system voltage.
  • The incoming and outgoing line termination arrangements must be confirmed with respect to the transmission line orientation.
  • The grade level and the equipment foundation levels must be determined based on the electrical site conditions and flood levels.
  • The switchyard layout configuration must be finalized based on considering the equipment arrangement and maintenance accessibility.
  • The earthing grid design must be developed and step potential and touch potential levels must be evaluated for the electrical safety.
  • A suitable lightning protection system must be designed for the switchyard.
  • Adequate yard lighting arrangements must be established for a safe operation and maintenance.
  • The necessary structural and foundation design parameters must be provided to the civil engineering team.
  • The cable routing system such as cable trenches (or) cable trays must be finalized.
  • The communication system requirements between the switchyard and control room must be defined.

During equipment installation planning the following points must be verified:

  • For circuit breakers the foundation level and operating cubicle arrangement must be finalized.
  • For isolators the operating height and foundation requirements must be confirmed.
  • For power transformers the oil drainage system and fire protection arrangements must be get finalized. 
  • Adequate maintenance (preventive) access and cable entry provisions must be provided for the transformers.
  • For lightning arresters the adequate electrical clearances must be ensured.
  • For bus post insulators the insulator height and mounting arrangements must be verified.
  • For instrument transformers (CTs and PTs) adequate spacing from the adjacent equipment must be maintained.

The cable routing system must be designed with the following considerations:

  • Main and branch cable trenches must be provided for the routing power and control cables.
  • The cable trench dimensions must be standardized while allowing the provision for future expansion.
  • Bay wise symmetry must be maintained in cable routing to ensure an organized installation and easier maintenance.

Proper access arrangements must be provided for equipment installation and maintenance:

  • Safe and adequate access to all the switchyard equipment must be ensured.
  • Maintenance access routes must be designed to facilitate the inspection and servicing activities.
  • Approach roads must be provided to allow transportation and installation of heavy equipment.

The control room design must address the following requirements:

  • The control room elevation and layout must be determined considering cable routing and accessibility.
  • Adequate space must be provided for protection panels, control panels, communication systems and auxiliary equipment.
  • Provision must be made for future expansion of control and protection systems.
  • Adequate ventilation and environmental control systems must be provided where ever required.

Maintenance provisions must be included in all switchyard design:

  • Dedicated maintenance areas and equipment handling provisions must be provided.
  • Adequate storage facilities and maintenance power tools must be arranged for the equipment servicing.

The switchyard design must incorporate the necessary safety precautions/measures:

  • Proper fencing and security arrangements must be installed around the switchyard.
  • Suitable fire protection systems must be provided for the equipment and cable installations.
  • Fire extinguishers and emergency response equipment must be installed at the appropriate locations.
  • Insulating mats, safety signage and warning boards must be provided to ensure a personnel safety.

The design must obtain all the necessary statutory approvals:

  • Approval must be obtained from the relevant electrical authorities and inspectorates.
  • Compliance with the power grid operator requirements and utility regulations must be ensured.
  • Necessary environmental and electrical safety clearances must be obtained before the project execution.